Contoh Soal Manajemen Proyek (Part II)

Berikut contoh soal dalam pelajaran manajemen proyek, silahkan disimak

 
1.         Which of the following is TRUE about a work breakdown structure?
a.       It contains work packages a feature in a linear, unstructured list
b.      Each item in the WBS represents a feature in the product scope
c.       The WBS represents all the work that must be done on the project
d.      The WBS is created by the product sponsor and stakeholders

Jawab :
C. The WBS represents all the work that must be done on the project

Alasan : Karena WBS digunakan untuk melakukan Breakdown atau memecahkan tiap proses pekerjaan menjadi lebih detail. Hal ini dimaksudkan agar proses perencanaan proyek memiliki tingkat yang lebih baik.

2.         Which is NOT an output a scope management process?
a.       Business Case
b.      WBS Dictionary
c.       Requested changes
d.      Accepted deliverables

Jawab :
A.    Business Case

Alasan : Karena business case tidak termasuk dalam output scope management process. Namun untuk menyediakan analisis nilai organisasi, biaya dan keuntungan, dan resiko dari beberapa alternative

3.         Which of the following is NOT TRUE about a work breakdown structure?
a.       It describes processes to define the scope, verify work, and manage scope changes
b.      It contains a graphical, hierarchical list of all work to be performed
c.       It can be broken down by project phase or deliverable
d.      It is an important element of the scope baseline

Jawab :
A.    It describes processes to define the scope, verify work, and manage scope changes

Alasan : karena untuk membuat wbs bukan untuk mendefinisikan bagian dari scope management tetapi karena sebuah proyek harus dibuat lebih manageable dengan cara mendetilkannya menjadi komponen tersendiri maka dibutuhkanlah WBS

4.         What is the correct order of the scope management processes?
a.       Define Scope, Create WBS, Collect Requirements, Scope Verification
b.      Collect Requirements, Control Scope, Create WBS, Scope Verification
c.       Collect Requirements, Define Scope, Create WBS, Scope Verification
d.      Collect Requirements, Scope Baseline, Define Scope, Control Scope


Jawab :
C.     Collect Requirements, Define Scope, Create WBS, Scope Verrification

Alasan : karena untuk scope management process terdapat 5 tahap yaitu Collect Requirements, Define Scope, Create WBS, dan Control Scope (Sesuai dengan PMBOK ® Guide edisi 4).

5.         You are managing a software project. Your team has been working for eight weeks, and so far the project in on track. The lead programmer comes to you with a problem: there is a work package that is causing trouble. Nobody seems to know who is responsible for it, the accounting department does not know what cost center to bill it against, and it’s not even clear exactly what work should be performed. Which of the following would BEST help this situation?
a.       Alternatives Analysis
b.      WBS Dictionary
c.       Scope Management Plan
d.      Scope Verification

Jawab :
B.     WBS Dictionary

Alasan :  karena tentang siapa yang bertanggung jawab terhadap sebuah proyek,  pengendalian keuangan apa yang mengasosiasikannya, dan menggambarkan pekerjaan yang terkait dengan proyek itu. Itu merupakan penggambaran yang cocok dengan WBS Dictionary

6.         The goal of Verify Scope is :
a.       To inspect the scope statement for defects so that it is correct
b.      To gain formal acceptance of the project deliverables from the sponsor and stakeholders
c.       To get everyone in the project working together toward a common goal
d.      To verify that all PMBOK® Guide processes are compiled with

Jawab:
B.     To gain formal acceptance of the project deliverables from the sponsor and stakeholders

Alasan : Verify Scope digunakan untuk mengecek apakah semua paket kerja telah selesai, dan mendapatkan stakeholder dan sponsor untuk menerima hasil kerja secara resmi.


7.         Historical information and lessons learned are part of :
a.       Organizational process assets
b.      Enterprise environmental factors
c.       Project management information system (PMIS)
d.      Work performance information

Jawab :
A.    Organizational process assets

Alasan : Historical Information adalah hal-hal seperti laporan dan data yang anda atau manajer proyek lain tulis di proyek sebelumnya dan disimpan di lemari arsip atau database. What lessons are learned? Itu adalah pelajaran yang  ditulis pada akhir proyek sebelumnya dan terjebak pada sebuah lemari file atau sebuah database. Dan sekarang pelajaran itu adalah asset lain yang dapat digunakan

8.         You’ve taken over as a project manager on a highway construction project, and the execution is already underway. Your sponsor tells you that moving forward, all asphalt be laid down with a 12” thickness. The scope statement and the WBS call for 9” thick asphalt. What is the BEST course of action?
a.       Look for a cheaper supplier so the cost impact is minimized
b.      Tell the sponsor that the work is already underway, so you can’t accommodate his request
c.       Refuse to after the plans until the change control system has been used
d.      Tell the team to accommodate the request immediately

Jawab :
C.     Refuse to after the plans until the change control system has been used

Alasan : perubahan sistem kontrol sangat utama dan tidak ada jalan lain sebelum sistem  itu di ubah sehingga tindakan terbaik yang utama menolak terlebih dahulu permintaan dari sponsor dan menunggu sampai sistem kontrol telah benar-benar di ubah untuk digunakan.

9.         Which of the following BEST describes the purpose of a traceability matrix?
a.       It describes how WBS Dictionary entries are traced to work packages, and how work packages are decomposed from deliverable
b.      It’s used to make sure that all of the sub-plans of the Project Management Plan have been created
c.       It helps you understand the source of each requirement, and how that requirement was verified in a later deliverable
d.      It used to trace the source of every change, so that you can keep track of them through the entire Control Scope process and verify that the change was properly implemented

Jawab :
c.       It helps you understand the source of each requirement, and how that requirement was verified in a later deliverable

Alasan : Sebuah Traceability Matriks adalah tabel yang digunakan untuk menelusuri kebutuhan untuk tes yang diperlukan untuk memverifikasi bahwa persyaratan tersebut terpenuhi. Salah satu tujuan dari Requirement Traceability Matrix yakni memastikan bahwa setiap dokumen harus dapat ditelusuri. Test case yang sudah dipersiapkan harus sesuai dengan spesifikasi kebutuhan yang sudah ditetapkan. Jika ada versi update, dokumen test case harus dapat ditelusuri dengan itu.


10.     It’s the end execution for a large highway construction project. The work has been done, and the workers are ready to pack up their equipment. The project manager and project sponsor have come by with specialists to check that each requirement has been met, and that all the work in the WBS has been performed. What process is being done?
a.       Control Scope
b.      Verify Scope
c.       Scope Testing
d.      Define Scope

Jawab :
B.     Verify Scope

Alasan : Karena verifikasi scope adalah waktu dimana sponsor dan stakeholder akan melihat dan menentukan hasil dari pengerjaan proyek secara formal dengan penuh ketelitian untuk memastikan apakah WBSnya telah cocok dengan pengerjaan proyek atau tidak

11.     You have just been put in change of a project that is already executing. While reviewing the project documentation, you discover that there is no WBS. You check the Scope Management Plan and discover that there should be one for this project. What is the BEST thing for you to do?
a.       Immediately alert the sponsor and make sure the project the project work stop
b.      Stop project work and create the WBS, and don’t let work continue until it’s created
c.       Make sure you closely manage communications to ensure the team doesn’t miss any undocumented work
d.      Mark it down in the lessons learned so it doesn’t happen on future projects

Jawab :
b. Stop Project work and create the WBS, and don’t let work continue until it’s created

Alasan : Hal yang paling penting sebuah WBS adalah jika Scope Management Plan anda mengatakan harus dilakukan, kemudian proyek anda sama sekali tidak bisa dilakukan tanpa WBS. Dan sebuah aturan umum adalah jika anda pernah temukan bahwa tidak ada nya WBS, anda harus selalu mengecek Scope Management Plan untuk mencari hal yang tidak sesuai dengan Scope Management Plan


12.     A project manager on an industrial design project finds that the sponsor wants to make a change to the scope after it has been added to the baseline, and needs to know the procedure for managing changes. What is the BEST place to look for this information ?
a.       WBS
b.      Scope management plan
c.       Change request from template
d.      Business case

Jawab :
b.      Scope Managemen Plan

Alasan : Dengan Scope Management Plan maka akan memberikan prosedur spesifik untuk mendefinisikan scope, breaking down of the work , verifikasi deliverable, dan mengatur perubahan scope.

13.     You have just started work on the Project Scope Statement. You are analyzing the expected deliverable, when you discover that one of them could be deliverable in three different ways. You select the best method for creating that deliverable. What is the BEST way to describe what you are doing ?
a.       Alternative Analysis
b.      Decomposition
c.       Define Scope
d.      Stakeholder Analysis

Jawab :
A.    Alternative Analysis

Alasan : Alternative Analysis adalah bagian dari definisi scope, dan lebih akurat untuk mendeskripsikan apa yang terjadi. Saat anda mencari beberapa cara bagaimana untuk membuat deliverable dan kemudian menentukan apa yg terbaik, maka itulah alternative analysis


14.     You’re the project manager on a software project. Your team has only completed half of the work, when the sponsor informs you that the project has been terminated. What is the BEST action for you to take?
a.       Verify the deliverables produced by the team against the scope, and document any place they do not match
b.      Call a team meeting to figure out how to spend the rest of the budget
c.       Work with the sponsor to see if there is any way to bring the project back
d.      Tell the team to stop working immediately

Jawab :
A.    Verify the deliverables produced by the team against the scope, and document any place they do not match

Alasan : Menurut PMBOK ® Guide. Ketika sebuah proyek dihentikan, anda masih harus menyelesaikan proses Verify Scope. Sehingga, anda dapat mendokumentasikan semua pekerjaan yang telah selesai dan pekerjaan yang belum selesai

15.     You are managing an industrial design project. One of your team members comes to you with a suggestion that will let you do more work while at the same time saving the project 15% of the budget. What is the BEST way for you to proceed?
a.       Tell the team to make the change because it will deliver more work for less money
b.      Refuse to make the change until a change request is documented and change control is performed
c.       Refuse to consider the change because it will affect the baseline
d.      Do a cost-benefit analysis and then make sure to inform the sponsor that the project scope changed

Jawab :
B.     Refuse to make the change until a change request is documented and change control is perfomed

Alasan : Anda tidak bisa semaunya membuat perubahan. Anda perlu mendokumentasikan permintaan perubahan melalui kendali perubahan. Jika disetujui, maka anda dapat memperbarui alur pekerjaan sesuai kesepakatan.

16.     You are the project manager for a telecommunications project. You are working on the project scope statement. Which of the following is NOT included in this document?
a.       Authorized for the project manager to work on the project
b.      Requirement that the deliverable must meet
c.       A description of the project objective
d.      The list of deliverable that must be created

Jawab :
A.    Authorized for the project manager to work on the project

Alasan : Sesuai dengan kegunaan dari project charter yaitu keterlibatan dari setiap fungsi dalam proyek akan tampak jelas. Sponsor dan project leader juga akan bisa memberikan arahan yang jelas dalam pengerjaan proyek hingga akhir. Berdasarkan kegunaan dari project charter dapat didapatkan bahwa manajer proyek tidak ada kewenangan untuk bekerja dalam proyek melainkan memberikan arahan yg jelas dalam pengerjaan proyek hingga akhir.


17.     Which of the following is NOT an input to Control Scope?
a.       WBS Dictionary
b.      Approved change requests
c.       Requested changes
d.      Project scope statement

Jawab :
c.       Request Changes

Alasan : Request Changes tidak termasuk dalam input Control Scope

18.     Which of these processes is not a part of Scope Management?
a.       Scope Identification
b.      Collect Requirements
c.       Control Scope
d.      Scope Verification

Jawab :
A.    Scope Identification

Alasan : Scope Identification bukanlah bagian dari Scope Management melainkan hanyalah proses yg dibuat-buat.

19.     You are the project manager for a new, and you want to save time creating the WBS. Which is the BEST way to do this?
a.       Make decomposition go faster by cutting down the number of deliverables
b.      Use a WBS from a previous project as a template
c.       Don’t create the WBS Dictionary
d.      Ask the sponsor to provide the work packages for each deliverable

Jawab :
B.     Use a WBS from a previous project as a template

Alasan : Cara termudah untuk membuat WBS template adalah menggunakan template yang telah digunakan pada proyek sebelumnya. Namun lewatkan output penting seperti WBS Dictionary atau buat sponsor untuk melakukan pekerjaan ini.

20.     The project manager for a design project is using the Define Scope process. Which BEST describes this ?
a.       Creating a document that lists all of the features of the product
b.      Creating a plan for managing changes to the scope baseline
c.       Creating a document that describes all of the work the team does to make the deliverable
d.      Creating a graphical representation of how the phases or deliverable decompose into work packages

Jawab :
C.     Creating a document that describes all of the work the team does to make the deliverable

Alasan : Output utama dari Define Scope adalah Scope Statement, dan jawaban C adalah deskripsi yang tepat dari scope statement


21.     You are the project manager for a construction project. You have completed project initiation activities, and you are now creating a document that describes processes to document the scope, decompose deliverable into work packages, verify that all work is complete, and manage changes to the baseline. What process are you performing?
a.       Develop Project Management Plan
b.      Define Scope
c.       Create WBS
d.      Develop Project Charter

Jawab :
A.    Develop Project Management Plan

Alasan : Prosedur dalam mengerjakan semua proses dari scope management  terdapat dalam Project Management Plan. Secara spesifik Scope Management Plan adalah sub-plan. Dan semua itu dibangun di dalam proses  Develop Project Management Plan


22.     You are a project manager working on a project. Your sponsor wants to know who a certain work package is assigned to, what control account to biii it against, and what work involved. What document do you refer to?
a.       Scope Management Plan
b.      WBS
c.       WBS Dictionary
d.      Scope Statement

Jawab :
c.       WBS Dictionary

Alasan : WBS Dictionary menunjukkan detail dari individual work packages dan berisi control account, pernyataan kerja, dan sumber pekerjaan.

24.     You are the project manager for a software. One of the teams discovers that if they deviate from the plan, they can actually skip one of the deliverable because it’s no longer necessary. They do the calculations, and realize they can save the customer 10% of the cost of the project without compromising the features in the product. They take this approach, and inform you the following week what they did during the status meeting. What is the BEST way to describe this situation?
a.       The project team has taken initiative and saved the customer money
b.      A dispute is resolved in favor of the customer
c.       The team informed the project manager of the change, but they should have informed the customer too
d.      The team did not follow the Control Scope process

Jawab :
D.    The team did not follow the Control Scope process

Alasan : Pada kasus ini tim seperti sangat membantu dalam proyek ini akan tetapi sesungguhnya tim ini meninggalkan rencana yang telah disepakati dan kemudian membuat perubahan proyek tanpa mendapatkan persetujuan dari sponsor dan stakeholder. Mereka mungkin menemukan shorcut yg lebih berguna. Tapi tidakkah mungkin bahwa shortcut tesebut telah ditolak oleh sponsor. Jadi karena itulah change control sangatlah penting

25.     Which of the following BEST describes the purpose of the project scope statement?
a.       It describes the features of the product of the project
b.      It is created before the scope management plan
c.       It decomposes deliverable into work packages
d.      It describes the objectives, requirements, and deliverable of the project, and the work needed to create them
Jawab :
D.It describes the objectives, requirements, and deliverable of the project, and the work needed to create them


Alasan :  Karena Project Scope Statement merupakan output dari Define Scope yang berfungsi untuk menggambarkan tujuan, persyaratan, proyek deliverable dan pekerjaan yang diperlukan untuk membuatnya

26.     A project manager at a cable and networking company is gathering requirements for a project to build a new version of their telecommunication equipment. Which of the following is NOT something that she will use?
a.       Specific descriptions of work packages that will be developed
b.      One-on-one interviews with the senior executives who need the new equipment for their teams
c.       An early working model of the telecommunications equipment to help get feedback from stakeholders
d.      Notes that she took while being “embedded” with the team that will eventually use equipment being developed

Jawab :
A.    Specific descriptions of work packages that will be developed

Alasan : Manajer proyek dalam hal ini sedang mengumpulkan kebutuhan dalam proyek itu sendiri. Jawaban yang tidak tepat adalah A karena merupakan proses pembuatan WBS

27.     Which of the following is NOT an output of Collect Requirements?
a.       Requirements Observations
b.      Requirements Traceability Matrix
c.       Requirements Documentation
d.      Requirements Management Plan

Jawab :
A.    Requirements Observations

Alasan :  Ada tiga output dari Collect Requirement yakni Requirements Documentation, Requirements Management Plan, dan Requirements Traceability Matrix. “Requirements Observations” bukanlah outputnya.